Update as of November 27, 2024
In November, the Childcare Project Team worked on the following:
o Architect sent project team a complete set of drawing to review. Once reviewed drawings are ready to issue cost consultant and energy modeler.
o Architect sent the project team a preliminary Modular Construction Class D cost estimate and will send a more refined analysis of the cost in the near future.
o Director of Operations completed BC Hydro authorization form for both facilities.
Full progress on the capital project is available at: https://www.sd59.bc.ca/district/capital-projects/child-care-facilities.