Update as of November 27, 2024
In November, the following progress occurred:
o Engineer, Director of Operations and Secretary-Treasurer met to discuss the tendering process rendering of the front of the school.
o Director of Operations and Secretary-Treasurer attended a Crescent Park PAC meeting where a slide deck presentation was provided to the PAC . PAC was given a copy of the rendering, site plan and floor plan to be posted at the school, as well as a copy of the presentation.
o Engineer and Director of Operations met to set schedule for tendering of the modular construction portion of the project.
Tentative Tender Schedule
o November 26, 2024 - Final meeting between electrical, mechanical and structural engineers
o December 2, 2024 - Post on BC Bid
o Mid December 2024 - Bidders site visit
o January 6, 2025 – Tender close and award
Full progress on the capital project is available at: https://www.sd59.bc.ca/district/capital-projects/crescent-park-expansion-project