Since September 20, 2024 the following have occurred:
• September 25, 2024
Project team met with architect to review design package and make recommendations.
• October 5, 2024
Tumbler Ridge site was surveyed.
• October 6, 2024
Dawson Creek site was surveyed.
• October 9, 2024
Project team met with architect to discuss final details. Falcon Engineering attended meeting to give a brief overview of the HVAC options.
• October 9, 2024
Geo Tech survey completed at Tumbler site.
• October 11, 2024
Falcon Engineering emailed the project team the 3 HVAC options for the facilities.
• October 16, 2024
Project team met with architect and Falcon Engineering to review 3 HVAC options and settled on a 4th option.
• October 16, 2024
Plumbing details were sent out to project team for review.
Full progress on the capital project is available at: https://www.sd59.bc.ca/district/capital-projects/child-care-facilities.