Child Care Facilities Updates - December 18, 2024

Update as of December 18, 2024

The following progress has been made since the November Board Meeting:

  • A meeting was held involving Director of Operations, the Architect, and the Engineer to discuss foundation options for the project. 
  • For both childcare facilities, the draft Class A cost estimate for traditional stick-build construction is currently under review by the Architect and will be issued for review next week.
  • The Class A cost estimate for the modular construction option is still being completed by the cost estimate consultant.
  • Coordination of site conditions for both facilities with the City of Dawson Creek and the District of Tumbler Ridge is still ongoing.
  • Structural and civil engineering coordination remains in progress.

 Next Steps:

  • Review the final costing once it is received and integrate any necessary adjustments into the design plans.
  • Continue with detailed design work to ensure all elements are resolved and ready for the next phase.
  • Maintain open communication with city representatives to ensure regulatory compliance and alignment.
  • Finalize the Class A cost estimates for both construction options.
  • Confirm site-specific requirements, including fire hydrant locations, in coordination with the City of Dawson Creek.

A full progress report is available at: 
https://www.sd59.bc.ca/district/capital-projects/child-care-facilities.

Erase Bullying

Erase is all about building safe and caring school communities. This includes empowering students, parents, educators and the community partners who support them to get help with challenges, report concerns to schools, and learn about complex issues facing students.

More Details

© School District 59.   All rights reserved.

Buses

Posted Route Status
11 hours ago Dawson Creek On Schedule
11 hours ago Chetwynd On Schedule

StrongStart

The StrongStart programs are running as scheduled.