Capital Project Update for New Child Care Facilities - February 19, 2025

Below are the significant developments in the Child Care Facility Projects since January 22, 2025. 

Next Steps:
January 6, 2025 - Architect and Engineer continued working on civil and structural drawings.

January 28, 2025 - Architect completed costing for stick building the childcare facilities

  • Tumbler childcare stick build cost $ 5.6m
  • Dawson childcare stick build cost $ 5.0m

January 30, 2025 - Architect and project team met to discuss costing and next steps.  Architect still awaiting modular build costing to compare to stick build.

February 3, 2025 - Project team begins licensing applications with Northern Health for both locations.

February 12, 2025 - Architect and Director of Operations met with the City of Dawson Creek to discuss fire hydrant requirements and next steps in the building permit process.

Please follow https://www.sd59.bc.ca/district/capital-projects for updates on these projects.

Erase Bullying

Erase is all about building safe and caring school communities. This includes empowering students, parents, educators and the community partners who support them to get help with challenges, report concerns to schools, and learn about complex issues facing students.

More Details

© School District 59.   All rights reserved.

Buses

No data is available at this time. This may mean that school buses are not running today, or current information is not yet available.

StrongStart

closed
open