Below are the significant developments in the Child Care Facility Projects since January 22, 2025.
Next Steps:
January 6, 2025 - Architect and Engineer continued working on civil and structural drawings.
January 28, 2025 - Architect completed costing for stick building the childcare facilities
- Tumbler childcare stick build cost $ 5.6m
- Dawson childcare stick build cost $ 5.0m
January 30, 2025 - Architect and project team met to discuss costing and next steps. Architect still awaiting modular build costing to compare to stick build.
February 3, 2025 - Project team begins licensing applications with Northern Health for both locations.
February 12, 2025 - Architect and Director of Operations met with the City of Dawson Creek to discuss fire hydrant requirements and next steps in the building permit process.
Please follow https://www.sd59.bc.ca/district/capital-projects for updates on these projects.